I propose to divide the project into four milestones/deliverables to produce a sequential progress report through the GSoC.
> They are NOT of equal sizes/time requirements.
*They are NOT of equal sizes/time* requirements.
#### **Milestone #1: Create a Bare-bone `package: mem0_dart`.**
@ -229,7 +230,9 @@ their final mentor evaluation (standard coding period)
* **Coding Period (June 2 - July 14)**
* **Week 1 (June 2 - June 8)**
<u>M#1 is delivered, comprising of a bare-bones package.</u> Work on M#2 begins in the latter half of the week.
<u>M#1 is delivered, comprising of a bare-bones package.</u>
Work on M#2 begins in the latter half of the week.
* **Week 2 (June 9 - June 15)**
Start of M#2 integration for the first two chosen vector database capable of basic vector operations(insert, search, delete, and get) are done, along with unit tests.
@ -244,7 +247,9 @@ their final mentor evaluation (standard coding period)
* **Week 5 (June 23 - June 29)**
Start of M#3 by integrating OpenAI and Gemini's LLM and embedding models.
This week will also contain steps of documenting the package for initial public release.
Mentor Reviews are requested.
*`The first public release of package mem0_dart:0.0.1 is made.`*
@ -252,7 +257,9 @@ their final mentor evaluation (standard coding period)
* **Week 6 (June 30 - July 6)**
Changes follow, from Mentor Review, if required.
Add support for other LLM and Embedding model providers(Since the same process has been done earlier this must be fairly easy to implement).
Final Mentor Review before Mid-term Evaluation is submitted.
* **Midterm Evaluation Submission (July 14 - July 18)**
@ -262,6 +269,7 @@ their final mentor evaluation (standard coding period)
* **Week 7 (July 14 - July 20)**
A significant portion of the week will be dedicated to testing all integrations thoroughly and addressing any bugs or issues identified.
Documentation is enhanced in the if no issues arise.
<u>Milestone #3 is delivered.</u>
@ -278,12 +286,15 @@ their final mentor evaluation (standard coding period)
* **Week 10 (August 4 - August 10)**
Continuation of the work done in Week 9.
Mentor Reviews are requested.
* **Week 11 (August 11 - August 17)**
The former half of the week acts as a buffer period in case any issues are confronted.
Documentation is enhanced in the buffer period if no issues arise.
<u>Milestone #4 is delivered.</u>
*`Third public release of the package at 0.0.3`*
@ -291,6 +302,7 @@ their final mentor evaluation (standard coding period)
* **Week 12 (August 18 - August 24)**
Final checks are made, and any supporting documents (such as example markdown files) are written.
The project Report is written and all tracking issues are labelled appropriately.
* **Final Week (August 25 - September 1)**